Gulf water and sandy shoreline at North Jetty Beach on Casey Key in Nokomis, Florida.

A Winter Guide to Parking, Road Work and Beach Food at Nokomis Beach and North Jetty

November 26, 2026

Sarasota County's oldest public beach gave up part of its parking lot to a road crew in the spring of 2025. Starting April 28, 2025, the county closed the section of the Nokomis Beach lot south of the playground, on the east side of Casey Key Road, and turned it into a staging area for rebuilding North Casey Key Road. The Herald-Tribune reported that the lot closure would last through fall 2027. By October 2025, Your Observer reported a barge and heavy machinery parked there, plus a smaller staging area at Blackburn Point Park.

The road project's schedule shapes a beach day here this winter more than anything else, and the staging closure is set to outlast it. The county's own project sheet, updated this month, targets spring 2027 for finishing the road. The lot closure was announced through fall 2027. Down at the south end of Casey Key, North Jetty Park has its own unfinished repairs, and as of late August the county said those had no construction schedule. Know which clock applies to which spot and a Saturday at the beach gets easier.

The two Casey Key beach parks, side by side

Location Latest county status, with date County timeline
North Casey Key Road, north segment Road temporarily shifted west while the permanent road is built, November 2026 update Construction finish spring 2027
North Casey Key Road, south segment Rebuild nearing completion; water-access stairs and final asphalt still to come, November 2026 update Construction finish spring 2027
Nokomis Beach lot south of the playground Closed for construction staging starting April 28, 2025 Announced through fall 2027
Nokomis Beach lifeguard tower, office and concession buildings Named in a FEMA environmental notice posted Sept. 1, 2026 No schedule published
North Jetty Park south parking along the jetty waterway Unavailable as of Aug. 26, 2026; restoration in preliminary design No construction schedule set as of Aug. 26, 2026
North Jetty concession contract Notice of Recommended Award posted Oct. 19, 2026 Award pending

The road crew up the key works out of the beach lot

The road work is concentrated on a short stretch. Sarasota County hired de Moya CHC Joint Venture LP to rebuild about half a mile of North Casey Key Road north of Blackburn Point Road and put up a permanent seawall, on a construction contract of $44,590,755.48. The 2024 storms left voids under the old road and damaged the barrier that protected it from erosion. Your Observer's October 2025 coverage put the project in two segments: 0.38 miles between 846 and 526 North Casey Key Road, and 0.15 miles from 332 to 230 North Casey Key Road.

The county's November 2026 update says the temporary wall is up. On the north end, the road has been moved temporarily west so crews can build the permanent road. On the south end, reconstruction is nearly done, with two items left: stairs from the roadway down to the water, and the final layer of asphalt. The county asks drivers to use caution through the work zone. The plan Your Observer described ends with the temporary road and bulkhead coming out and stone riprap going in along the shore.

The county's current sheet puts construction finish in spring 2027, close to the March 2027 date Your Observer reported in October 2025. The staging area at Nokomis Beach was announced to stay closed through fall 2027, and the county also lists the project's design work as finishing in summer 2027. Bike rides and drives up North Casey Key Road should get smoother through the spring. The Nokomis Beach lot is on a longer schedule.

Some beach parking has already moved over the bridge. Your Observer reported in October 2025 that with part of the Nokomis Beach lot closed, some beachgoers were looking for spots across the bridge on Albee Road, including the lot at Pelican Alley, the waterfront restaurant there. Pelican Alley and Pop's Sunset Grill are both long-standing Albee Road spots. Their lots belong to their customers, so if you plan to eat there before or after the beach, go as a customer and leave the beach parking to the beach.

Three Nokomis Beach buildings are in federal review

The road isn't the only project with ties to Nokomis Beach. On Sept. 1, 2026, Sarasota County posted a FEMA environmental and historic preservation public notice naming three Nokomis Beach structures: the lifeguard tower, the office building and the concession building.

A month before that notice, a lifeguard tower at the beach had its own bad day. On Aug. 6, 2026, WWSB reported that lightning struck a lifeguard tower at Nokomis Beach North and set it on fire. Beachgoers and staff had already been cleared from the beach because of the storm, and no one was hurt. A worker at the beach snack shack told the station they saw the strike during heavy rain.

The county's facility listing for Nokomis Beach Park includes beach access, a boat ramp, a concession, lifeguards, picnic shelters and restrooms. The park is open 6 a.m. to 10 p.m., and the boat ramp is open 24 hours a day. With three of the park's buildings named in the FEMA notice, check the county's parks pages before a day planned around a particular shelter or the concession.

North Jetty reopened first and is still missing a lot

At the south tip of Casey Key, North Jetty Park started its comeback earlier. The Herald-Tribune reported that the park partly reopened on March 1, 2025, with the north and east parking lots, the lifeguard station, public restrooms and the North Jetty Grille. The old North Jetty Fish Camp was destroyed in the hurricanes, and at the time the concession operator said it hoped to bring a similar feel to the Grille.

The parking along the jetty waterway was still closed in late summer. In August 2026, a question posted on the county's concession bid page said that roughly 50 to 100 spaces on the south side of the lot remained unavailable because of hurricane damage. The county answered on Aug. 26, 2026, that the damaged areas of the park, including the grounds, were "being evaluated and designed for restoration," that the project was in preliminary design and preconstruction, and that "a construction schedule has not yet been established." Between the closed staging section at Nokomis Beach and the closed south side at North Jetty, both of Casey Key's public beach parks went into the fall with less parking than they had before the 2024 storms.

The food stand at North Jetty is in the middle of a contract change. On Sept. 2, 2026, the county confirmed that Shark Tooth Beach Concessions/North Jetty Grille was running the concession. The county reopened the contract to bids: a pre-bid site visit was held Aug. 31 and an evaluation meeting Oct. 19. A Notice of Recommended Award was posted Oct. 19, 2026, and the procurement portal still lists the award as pending. The county's park directory lists North Jetty at the same 6 a.m. to 10 p.m. hours as Nokomis Beach, with beach access, fishing, lifeguards, picnic shelters, restrooms and a concession.

Planning a winter beach day around the schedules

The beach itself runs on its usual daily routine. Visit Sarasota's February 2026 guide listed Shark Tooth Beach Concessions at 208 S. Casey Key Road, open 10 a.m. to 4 p.m., and North Jetty Grille at 1000 S. Casey Key Road, open 8:30 a.m. to 4:30 p.m. It also listed a food and beverage trolley Wednesday through Sunday, 11 a.m. to 6 p.m. According to the same guide, the menus run from chicken and waffles to Philly cheesesteaks and nachos, the cold brew is roasted by Black Gold Coffee of Venice, and the house cocktails include The Shark Bite and The Jetty Juice. Shark Tooth rents beach gear at its Nokomis Beach location and also has rentals at North Jetty. Hours can change with the season and the contract, so confirm them before you plan lunch around the stand.

The evening routine gives you the best shot at parking. Visit Sarasota's June 2026 guide puts the Nokomis Drum Circle at 207 Casey Key Road. The guide says it meets Sunday evenings year-round, starting about an hour before sunset, and also on Wednesday evenings. Sunset in late November comes early, so the circle starts in late afternoon. That's around when the daytime crowd starts to leave the Nokomis Beach lot, after the concession window closes.

A few practical habits help through spring. Plan on fewer spaces than you remember at both parks, and pick a beach based on what you want that day. North Jetty has the Grille and its reopened north and east lots. Nokomis Beach has the drum circle, the boat ramp and the Albee Road restaurants across the bridge. If you head north on Casey Key Road toward Blackburn Point, expect the north segment to run on its temporary shifted alignment until the county finishes the permanent road. Our post on the Blackburn Point Bridge's centennial covers the swing bridge at that end of the key, and our Venice Beach update covers the beach across the inlet from North Jetty.

Casey Key's two beach parks are a big part of daily life in Nokomis. If you have questions about life in Nokomis, or about how Casey Key Road and the beach parks fit the day-to-day you have in mind, Sarasota Neighborhood Experts can share what we know. Visit our Nokomis neighborhood page or reach out. Let's Connect — Start Your Sarasota Search.